← Taiwan Semiconductor Manufacturing Company Limited

TSM · Forward model · Wei case

The Wei case, 20 quarters out

Each segment is projected from its own operating driver, rolled up into consolidated cash flow, and discounted back to a fair value per share. The assumptions below are editable — change them and every number on this page moves with them.

TSMC has no reportable segments in the Microsoft sense - it is a single foundry business and reports one consolidated profit and loss. What it publishes every quarter, on one slide of its earnings deck, is revenue BY PLATFORM as a percentage of net revenue: High Performance Computing, Smartphone, Internet of Things, Automotive, Digital Consumer Electronics and Others. Those six percentages sum to exactly 100 in all eight quarters here, so multiplying them by the reported dollar revenue gives six lines that reconcile to the consolidated total exactly. That is the whole basis of this model's verticals, and its limitation: the percentages are WHOLE NUMBERS, so every line carries up to half a point of rounding - about $200M a quarter on a $40.2B base, which is half the DCE line and a quarter of the Others line. Read the two small platforms as indicative and the three large ones as sound. What TSMC does NOT publish is any economics by platform. There is no gross margin, no operating margin, no capital expenditure and no capacity by platform - only consolidated figures - so all six verticals here carry the SAME margin and the SAME capital intensity, and the split does no economic work at all. It changes the revenue path and nothing else. The margin used is the disclosed 60.3% operating margin plus depreciation and amortisation added back at 15.14% of revenue, the first-half 2026 rate, giving 75.4%. There is no corporate overhead layer because there is nothing unallocated to put in it. One number in that add-back deserves attention: TSMC's depreciation was NT$359.5bn in the first half of 2026 against NT$359.0bn in the first half of 2025 - essentially FLAT - while capital expenditure ran at NT$496bn in the basis quarter alone. The fabs being built now are not yet in service, so the depreciation from this capital wave has barely started to arrive. Finally, the driver: TSMC publishes wafer shipments only in total (4,336 thousand 12-inch equivalents in the basis quarter) and gives no capacity or shipment figure per platform, so all six verticals run growth drivers. A per-platform wafer driver would have to assume every platform earns the same revenue per wafer, which is the one thing that is certainly false when HPC sits on 2-nanometer and IoT sits on mature nodes. A seventh vertical, Tesla AI5, is carried at ZERO in every reported quarter and starts in 2027. It is not a TSMC disclosure of any kind - TSMC has never named Tesla as a customer, never mentioned AI5 and publishes no wafer price - and it exists on this page to make one question answerable: what is a flagship automotive AI design win worth to a company running at $45bn a quarter? The arithmetic is two million cars a year at two half-reticle dies each, so four million chips or one million a quarter, at roughly $150 of TSMC revenue per die - about $22k a wafer over some 175 good dies, plus packaging. That is $153M in its first quarter, growing to $225M by 2031 as Optimus and training clusters lift the die count toward 1.8 million a quarter. It never exceeds 0.28% of revenue and it moves base fair value by one dollar, from $472.80 to $473.80. Note also that Tesla's EXISTING silicon is already inside the Automotive and HPC lines, which are projected from history that contains it, so this vertical must be read as incremental AI5 volume above the current run rate or it double-counts.

C.C. Wei's version: AI demand is structural rather than cyclical, TSMC's leading-edge monopoly holds through 2nm and A13, and the company keeps both the volume and the price. Every platform is lifted, because the claim is about the foundry rather than one end market. Two things this case does NOT contain. TSMC has published no multi-year revenue target - the furthest forward number in the filings is a single full-year growth rate - so there is no stated claim to test this against, unlike the other founder cases on this site. And at 11x terminal revenue the exit multiple is doing most of the work here; the operating assumptions on their own do not get close. Read it as the price of believing the monopoly persists for five years, not as a model of it.

TSM REVENUE MODEL

Latest: $175.10B (2031Q2E)

Period Value
2024Q3 $23.50B
2024Q4 $26.88B
2025Q1 $25.53B
2025Q2 $30.07B
2025Q3 $33.10B
2025Q4 $33.73B
2026Q1 $35.90B
2026Q2 $40.20B
2026Q3E $46.00B
2026Q4E $51.95B
2027Q1E $58.14B
2027Q2E $64.20B
2027Q3E $70.27B
2027Q4E $76.34B
2028Q1E $82.42B
2028Q2E $88.53B
2028Q3E $94.69B
2028Q4E $100.94B
2029Q1E $107.30B
2029Q2E $113.81B
2029Q3E $120.50B
2029Q4E $127.41B
2030Q1E $134.56B
2030Q2E $141.99B
2030Q3E $149.73B
2030Q4E $157.81B
2031Q1E $166.26B
2031Q2E $175.10B

What drives each segment

High Performance Computing

Growth path
Basis quarter$26.53B
Final quarter$153.94B
Implied CAGR+42%
Share of revenue, final quarter88%
PV of segment cash flow$621.40B

Two thirds of TSMC and effectively all of its growth. AI accelerators, datacenter CPUs and GPUs, and high-end compute - the platform every AI chip designer in the world routes through. It was 51% of revenue eight quarters ago and 66% now, and it grew 20% sequentially in the basis quarter while the company grew 12%. TSMC does not break out an AI line; AI sits inside this one, and the company will not size it. What makes this platform different from the other five is that it is the one bidding for leading-edge capacity: 2-nanometer began contributing revenue this quarter and 7-nanometer and below is 77% of wafer revenue.

Last four quarters
2025 Q3 $18.87B Estimated
2025 Q4 $18.55B Estimated
2026 Q1 $21.90B Estimated
2026 Q2 $26.53B Estimated
AI acceleratorsDatacenter CPUs and GPUsHigh-end compute
Sequential growth +17.0%/qtr decaying toward +2.5% 17% a quarter against the 20% just delivered. Still four times the company's terminal rate, and decaying from the start.
High Performance Computing

Latest: $153.94B (2031Q2E)

Period Value
2024Q3 $11.98B
2024Q4 $14.25B
2025Q1 $15.06B
2025Q2 $18.04B
2025Q3 $18.87B
2025Q4 $18.55B
2026Q1 $21.90B
2026Q2 $26.53B
2026Q3E $31.97B
2026Q4E $37.58B
2027Q1E $43.26B
2027Q2E $48.98B
2027Q3E $54.71B
2027Q4E $60.44B
2028Q1E $66.17B
2028Q2E $71.94B
2028Q3E $77.75B
2028Q4E $83.64B
2029Q1E $89.65B
2029Q2E $95.79B
2029Q3E $102.12B
2029Q4E $108.65B
2030Q1E $115.42B
2030Q2E $122.46B
2030Q3E $129.80B
2030Q4E $137.48B
2031Q1E $145.51B
2031Q2E $153.94B

Assumptions & reasoning

  • Revenue here is total company revenue multiplied by the platform percentage TSMC publishes on one slide of its quarterly deck. The percentages are whole numbers and sum to exactly 100 in all eight quarters, so the six lines reconcile to reported revenue exactly - but each line carries up to half a percentage point of rounding, which on this platform is about $200M.
  • TSMC publishes no revenue, no margin and no capacity for HPC. It publishes a percentage of revenue and a sequential growth rate, and nothing else - which is why this vertical has a growth driver and the same margin as the other five.
  • The one volume metric TSMC does publish is company-wide: 4,336 thousand 12-inch equivalent wafers in the basis quarter, up 3.9% sequentially against revenue up 12.0%. The gap is price and mix - blended revenue per wafer rose to about $9,300 - and almost all of it is this platform moving to leading-edge nodes.
  • Two-nanometer contributed 3% of wafer revenue for the first time this quarter and 7-nanometer and below reached 77%. That node ramp is the physical event behind this platform's growth, and TSMC guides gross margin DOWN to 65-67% next quarter partly because of it.

Smartphone

Growth path
Basis quarter$8.84B
Final quarter$11.92B
Implied CAGR+6%
Share of revenue, final quarter7%
PV of segment cash flow$74.78B

The platform HPC is taking share from. $8.8B of revenue, 22% of the company, down 4% sequentially in a quarter when the company grew 12% - and down from 34% of revenue two years ago. It is not shrinking in dollars so much as being outgrown: smartphone revenue is roughly where it was a year ago while HPC has more than doubled. It remains the second-largest platform and the one with the most seasonal shape, since flagship silicon is built in the middle of the calendar year for autumn launches.

Last four quarters
2025 Q3 $9.93B Estimated
2025 Q4 $10.79B Estimated
2026 Q1 $9.33B Estimated
2026 Q2 $8.84B Estimated
Application processorsModem and RFFlagship smartphone silicon
Sequential growth +0.5%/qtr decaying toward +0.5% 0.5% a quarter. It fell 4% in the basis quarter and is flat year over year; this is being outgrown, not shrinking.
Smartphone

Latest: $11.92B (2031Q2E)

Period Value
2024Q3 $7.99B
2024Q4 $9.41B
2025Q1 $7.15B
2025Q2 $8.12B
2025Q3 $9.93B
2025Q4 $10.79B
2026Q1 $9.33B
2026Q2 $8.84B
2026Q3E $8.98B
2026Q4E $9.11B
2027Q1E $9.25B
2027Q2E $9.39B
2027Q3E $9.53B
2027Q4E $9.67B
2028Q1E $9.82B
2028Q2E $9.97B
2028Q3E $10.12B
2028Q4E $10.27B
2029Q1E $10.42B
2029Q2E $10.58B
2029Q3E $10.74B
2029Q4E $10.90B
2030Q1E $11.07B
2030Q2E $11.23B
2030Q3E $11.40B
2030Q4E $11.57B
2031Q1E $11.75B
2031Q2E $11.92B

Assumptions & reasoning

  • Down 4% sequentially in a quarter when the company grew 12%, and down from 34% of revenue to 22% in two years. The dollars are roughly flat year over year; the share loss is HPC growing, not smartphone shrinking.
  • This is the most seasonal platform TSMC has - flagship silicon is built mid-year for autumn launches - so a single sequential print is a poor guide. The eight quarters here run +16%, +17%, -22%, +7%, +19%, +11%, -11%, -4%.
  • Smartphone competes with HPC for the same leading-edge capacity. When TSMC says demand exceeds supply, this is the platform that gets rationed, which is a reason to model it flat rather than growing.

Internet of Things

Growth path
Basis quarter$2.01B
Final quarter$3.55B
Implied CAGR+12%
Share of revenue, final quarter2%
PV of segment cash flow$20.05B

$2.0B, 5% of revenue, up 4% sequentially. Sensors, connectivity and edge silicon, mostly on mature and specialty nodes rather than leading edge. It grew 35% in one quarter two years ago and fell 15% in another, so the quarter-to-quarter path says less about the platform than about a handful of customers' inventory cycles. At 5% of revenue it is carried because TSMC publishes it, not because it decides anything.

Last four quarters
2025 Q3 $1.66B Estimated
2025 Q4 $1.69B Estimated
2026 Q1 $2.15B Estimated
2026 Q2 $2.01B Estimated
SensorsConnectivityEdge compute
Sequential growth +3.0%/qtr decaying toward +1.5% 3% a quarter against +4% delivered. The eight-quarter path swings from -15% to +35%, so a mid-single digit is the honest read.
Internet of Things

Latest: $3.55B (2031Q2E)

Period Value
2024Q3 $1.65B
2024Q4 $1.34B
2025Q1 $1.28B
2025Q2 $1.50B
2025Q3 $1.66B
2025Q4 $1.69B
2026Q1 $2.15B
2026Q2 $2.01B
2026Q3E $2.09B
2026Q4E $2.17B
2027Q1E $2.24B
2027Q2E $2.32B
2027Q3E $2.39B
2027Q4E $2.46B
2028Q1E $2.53B
2028Q2E $2.61B
2028Q3E $2.68B
2028Q4E $2.75B
2029Q1E $2.83B
2029Q2E $2.90B
2029Q3E $2.98B
2029Q4E $3.05B
2030Q1E $3.13B
2030Q2E $3.21B
2030Q3E $3.29B
2030Q4E $3.38B
2031Q1E $3.46B
2031Q2E $3.55B

Assumptions & reasoning

  • Five percent of revenue and the most erratic sequential path of any platform: +35%, -15%, -9%, +14%, +20%, +3%, +12%, +4% across the eight quarters shown. That is customer inventory rather than end demand.
  • Mostly mature and specialty nodes, so it does not compete for the leading-edge capacity that constrains HPC and smartphone. It is the platform least exposed to the 2-nanometer ramp in either direction.

Automotive

Growth path
Basis quarter$1.61B
Final quarter$3.37B
Implied CAGR+16%
Share of revenue, final quarter2%
PV of segment cash flow$17.97B

$1.6B, 4% of revenue, up 15% sequentially - the second-fastest platform in the basis quarter. ADAS, EV powertrain and in-vehicle compute. Automotive silicon has been through a two-year inventory correction and the sequential prints here have swung from -7% to +18% without much trend. It is the platform with the longest design-in cycles and the least sensitivity to the AI question that decides the rest of this model.

Last four quarters
2025 Q3 $1.66B Estimated
2025 Q4 $1.69B Estimated
2026 Q1 $1.44B Estimated
2026 Q2 $1.61B Estimated
ADASEV powertrainIn-vehicle compute
Sequential growth +5.0%/qtr decaying toward +2.0% 5% a quarter against +15% delivered, which came off an inventory correction rather than a trend.
Automotive

Latest: $3.37B (2031Q2E)

Period Value
2024Q3 $1.18B
2024Q4 $1.08B
2025Q1 $1.28B
2025Q2 $1.50B
2025Q3 $1.66B
2025Q4 $1.69B
2026Q1 $1.44B
2026Q2 $1.61B
2026Q3E $1.71B
2026Q4E $1.80B
2027Q1E $1.89B
2027Q2E $1.97B
2027Q3E $2.06B
2027Q4E $2.14B
2028Q1E $2.22B
2028Q2E $2.30B
2028Q3E $2.38B
2028Q4E $2.47B
2029Q1E $2.55B
2029Q2E $2.63B
2029Q3E $2.72B
2029Q4E $2.80B
2030Q1E $2.89B
2030Q2E $2.98B
2030Q3E $3.08B
2030Q4E $3.17B
2031Q1E $3.27B
2031Q2E $3.37B

Assumptions & reasoning

  • Up 15% sequentially, the second-fastest platform in the basis quarter, but the eight-quarter path is +6%, +6%, +14%, +0%, +18%, -1%, -7%, +15% - a platform coming out of an inventory correction rather than one compounding.
  • Automotive design-in cycles run years rather than quarters, so this line is the least sensitive of the six to the AI capacity question that decides the rest of the model.

Digital Consumer Electronics

Growth path
Basis quarter$402M
Final quarter$628M
Implied CAGR+9%
Share of revenue, final quarter0%
PV of segment cash flow$3.73B

$0.4B and 1% of revenue - televisions, set-top boxes and consumer silicon. It is the smallest platform TSMC reports and the one most distorted by rounding: at a whole-percentage disclosure, 1% of a $40.2B quarter could be anything from $200M to $600M. It is carried because TSMC publishes it separately, and the honest thing to say is that its projection cannot be more precise than the disclosure it comes from.

Last four quarters
2025 Q3 $331M Estimated
2025 Q4 $337M Estimated
2026 Q1 $359M Estimated
2026 Q2 $402M Estimated
Televisions and set-top boxesConsumer silicon
Sequential growth +2.0%/qtr decaying toward +1.0% 2% a quarter. At 1% of revenue disclosed as a whole number, no growth rate here can be more precise than the source.
Digital Consumer Electronics

Latest: $628M (2031Q2E)

Period Value
2024Q3 $235M
2024Q4 $269M
2025Q1 $255M
2025Q2 $301M
2025Q3 $331M
2025Q4 $337M
2026Q1 $359M
2026Q2 $402M
2026Q3E $414M
2026Q4E $426M
2027Q1E $437M
2027Q2E $448M
2027Q3E $459M
2027Q4E $470M
2028Q1E $480M
2028Q2E $491M
2028Q3E $502M
2028Q4E $513M
2029Q1E $523M
2029Q2E $534M
2029Q3E $546M
2029Q4E $557M
2030Q1E $568M
2030Q2E $580M
2030Q3E $592M
2030Q4E $604M
2031Q1E $616M
2031Q2E $628M

Assumptions & reasoning

  • One percent of revenue, disclosed as a whole number. The true figure could be anywhere between 0.5% and 1.5%, which is $200M to $600M on a $40.2B quarter - a range wider than the line itself. No projection here can be more precise than that.
  • It is carried separately because TSMC reports it separately. Folding it into Others would be tidier and would misstate what the company publishes.

Others

Growth path
Basis quarter$804M
Final quarter$1.42B
Implied CAGR+12%
Share of revenue, final quarter1%
PV of segment cash flow$8.02B

$0.8B and 2% of revenue - the residual TSMC does not assign to the five named platforms. Like DCE it is a whole-percentage line and carries the same rounding imprecision. It exists here so the six verticals sum to reported revenue rather than to 98% of it.

Last four quarters
2025 Q3 $662M Estimated
2025 Q4 $675M Estimated
2026 Q1 $718M Estimated
2026 Q2 $804M Estimated
Unassigned platforms
Sequential growth +3.0%/qtr decaying toward +1.5% 3% a quarter. A residual line at 2% of revenue; the rate is a placeholder, not a forecast.
Others

Latest: $1.42B (2031Q2E)

Period Value
2024Q3 $470M
2024Q4 $538M
2025Q1 $511M
2025Q2 $601M
2025Q3 $662M
2025Q4 $675M
2026Q1 $718M
2026Q2 $804M
2026Q3E $836M
2026Q4E $868M
2027Q1E $898M
2027Q2E $927M
2027Q3E $956M
2027Q4E $985M
2028Q1E $1.01B
2028Q2E $1.04B
2028Q3E $1.07B
2028Q4E $1.10B
2029Q1E $1.13B
2029Q2E $1.16B
2029Q3E $1.19B
2029Q4E $1.22B
2030Q1E $1.25B
2030Q2E $1.29B
2030Q3E $1.32B
2030Q4E $1.35B
2031Q1E $1.39B
2031Q2E $1.42B

Assumptions & reasoning

  • The residual TSMC does not assign to a named platform, at 2% of revenue. It exists in this model so the six verticals sum to reported revenue rather than to 98% of it.
  • Like DCE this is a whole-percentage disclosure on a $40B base, so its dollar value carries roughly $200M of rounding either way and its growth rate should not be read closely.

Tesla AI5

Units × price
Basis quarter$0
Final quarter$274M
Share of revenue, final quarter0%
PV of segment cash flow$1.33B

A line that does not exist yet, carried at zero across every reported quarter and starting in 2027. Tesla's AI5 is a roughly half-reticle inference die that Musk has said will be built at TSMC, two per car, against a stated ambition of two million cars a year. TSMC has never named Tesla as a customer, never mentioned AI5, and publishes no wafer price, so every number on this line is an outside estimate rather than a disclosure. It is here to make one question answerable on the page: what would a flagship automotive AI win actually be worth to a company running at $45bn a quarter? The answer, on the arithmetic below, is about half a percent of revenue - which is itself the finding.

Last four quarters
2025 Q3 $0 Reported
2025 Q4 $0 Reported
2026 Q1 $0 Reported
2026 Q2 $0 Reported
AI5 inference die for vehiclesAI5 for OptimusAI5 for training clusters
Units 1000000/qtr growing +3.0% per quarter 1,000,000 dies a quarter: two million cars a year at two AI5 dies each. Tesla's ambition, not a TSMC number.
Price per unit $150 drifting -1.0% per quarter $150 a die: roughly $22k a wafer over ~175 good half-reticle dies, plus packaging and test. An estimate.
Tesla AI5

Latest: $274M (2031Q2E)

Period Value
2024Q3 $0.00
2024Q4 $0.00
2025Q1 $0.00
2025Q2 $0.00
2025Q3 $0.00
2025Q4 $0.00
2026Q1 $0.00
2026Q2 $0.00
2026Q3E $0.00
2026Q4E $0.00
2027Q1E $158M
2027Q2E $162M
2027Q3E $167M
2027Q4E $173M
2028Q1E $178M
2028Q2E $184M
2028Q3E $190M
2028Q4E $196M
2029Q1E $203M
2029Q2E $210M
2029Q3E $217M
2029Q4E $224M
2030Q1E $232M
2030Q2E $239M
2030Q3E $248M
2030Q4E $256M
2031Q1E $265M
2031Q2E $274M

Assumptions & reasoning

  • Zero in every reported quarter, by construction. Tesla already buys silicon from TSMC and that revenue is inside the Automotive and HPC lines already; this vertical is the INCREMENTAL AI5 ramp above the current run rate, and reading it any other way double-counts.
  • The arithmetic: two million cars a year at two dies each is four million chips, or one million a quarter. At roughly $150 of TSMC revenue per chip - about $22k a wafer over some 175 good half-reticle dies, plus packaging - that is about $150M a quarter, or $600M a year.
  • The chip count grows toward 1.8 million a quarter, which is where Optimus and training clusters would take it. At $150 a chip that is $270M a quarter. A reader who wants the $250M a quarter that circulates for this programme is implicitly assuming roughly six to eight million AI5 dies a year, which is cars plus everything else, not cars alone.
  • At its peak this line is about half a percent of TSMC revenue and moves fair value by cents. That is the point of carrying it: a flagship automotive design win at a company this size is a rounding error, and the model says so explicitly rather than leaving it to intuition.
Scenarios

Where each case comes from

Bear case — primary sources

The primary sources this case is built from — filings, calls and posts. Where they are claims by an interested party rather than disclosures, every number in the Bear column is what happens if they are taken at face value.

First-half 2026 consolidated statements - the depreciation that has not arrived

Bull case — primary sources

The primary sources this case is built from — filings, calls and posts. Where they are claims by an interested party rather than disclosures, every number in the Bull column is what happens if they are taken at face value.

Wei case — primary sources

The primary sources this case is built from — filings, calls and posts. Where they are claims by an interested party rather than disclosures, every number in the Wei column is what happens if they are taken at face value.

Valuation

From cash flow to fair value

Present value of free cash flow, 20 quarters$612.77B
Terminal-year revenue$648.90B
Terminal-year EBITDA$497.93B
Exit multiple, on revenue11.0x
Terminal value$7.14T
Discounted at 10.0% a year, terminal value becomes$4.43T
Enterprise value$5.04T
Net cash$78.68B
Equity value$5.12T
Shares5.19B
Fair value per share$987.87
Against the current price of $427.30+131%

10% on a business with $78.7B of net cash and a 60% operating margin, marked up for a manufacturing base concentrated on one island and an end market - AI - that supplies all of the growth. The exit multiple is the number to argue with, and unusually so here: TSMC publishes no multi-year target, so nineteen of the twenty projected quarters rest on it. 8x terminal revenue on the roughly 72% terminal EBITDA margin in this model is about 11x EBITDA, which is a defensible multiple for a capital-intensive monopoly, against the 12x forward revenue the shares carry today.

Read the other way round: at $427.30 the market is paying 3.8x terminal-year revenue, holding every other assumption on this page fixed. That is the number to argue about.

Quarter by quarter

The projected path

Quarter High Performance ComputingSmartphoneInternet of ThingsAutomotiveDigital Consumer ElectronicsOthersTesla AI5 Revenue YoY EBITDA Capex FCF R40 PV of FCF
2026 Q3E $31.97B$8.98B$2.09B$1.71B$414M$836M$0 $46.00B +39% $36.41B $17.34B $15.64B +73 $15.27B
2026 Q4E $37.58B$9.11B$2.17B$1.80B$426M$868M$0 $51.95B +54% $40.99B $18.98B $18.05B +89 $17.21B
2027 Q1E $43.26B$9.25B$2.24B$1.89B$437M$898M$158M $58.14B +62% $45.74B $20.63B $20.60B +97 $19.17B
2027 Q2E $48.98B$9.39B$2.32B$1.97B$448M$927M$162M $64.20B +60% $50.38B $22.17B $23.13B +96 $21.03B
2027 Q3E $54.71B$9.53B$2.39B$2.06B$459M$956M$167M $70.27B +53% $55.00B $23.67B $25.69B +89 $22.81B
2027 Q4E $60.44B$9.67B$2.46B$2.14B$470M$985M$173M $76.34B +47% $59.61B $25.12B $28.28B +84 $24.51B
2028 Q1E $66.17B$9.82B$2.53B$2.22B$480M$1.01B$178M $82.42B +42% $64.22B $26.55B $30.89B +79 $26.14B
2028 Q2E $71.94B$9.97B$2.61B$2.30B$491M$1.04B$184M $88.53B +38% $68.85B $27.97B $33.52B +76 $27.70B
2028 Q3E $77.75B$10.12B$2.68B$2.38B$502M$1.07B$190M $94.69B +35% $73.50B $29.39B $36.17B +73 $29.19B
2028 Q4E $83.64B$10.27B$2.75B$2.47B$513M$1.10B$196M $100.94B +32% $78.22B $30.82B $38.87B +71 $30.63B
2029 Q1E $89.65B$10.42B$2.83B$2.55B$523M$1.13B$203M $107.30B +30% $83.02B $32.28B $41.61B +69 $32.02B
2029 Q2E $95.79B$10.58B$2.90B$2.63B$534M$1.16B$210M $113.81B +29% $87.94B $33.77B $44.42B +68 $33.37B
2029 Q3E $102.12B$10.74B$2.98B$2.72B$546M$1.19B$217M $120.50B +27% $92.98B $35.31B $47.29B +67 $34.69B
2029 Q4E $108.65B$10.90B$3.05B$2.80B$557M$1.22B$224M $127.41B +26% $98.19B $36.92B $50.25B +66 $36.00B
2030 Q1E $115.42B$11.07B$3.13B$2.89B$568M$1.25B$232M $134.56B +25% $103.59B $38.59B $53.30B +65 $37.28B
2030 Q2E $122.46B$11.23B$3.21B$2.98B$580M$1.29B$239M $141.99B +25% $109.20B $40.34B $56.47B +65 $38.57B
2030 Q3E $129.80B$11.40B$3.29B$3.08B$592M$1.32B$248M $149.73B +24% $115.04B $42.18B $59.75B +64 $39.85B
2030 Q4E $137.48B$11.57B$3.38B$3.17B$604M$1.35B$256M $157.81B +24% $121.14B $44.11B $63.17B +64 $41.14B
2031 Q1E $145.51B$11.75B$3.46B$3.27B$616M$1.39B$265M $166.26B +24% $127.53B $46.15B $66.73B +64 $42.43B
2031 Q2E $153.94B$11.92B$3.55B$3.37B$628M$1.42B$274M $175.10B +23% $134.21B $48.29B $70.45B +64 $43.75B

Every row is projected. A year-over-year change is shown only where the quarter it compares against exists — an em dash means there is no comparable quarter, not a flat year.

Track record

Model revisions

Assumptions are marked to reality as each quarter prints. Every change is appended here, with the fair value the model produced at the time, so the model's own history stays visible.

DateChangedFair value thenNote
2026-08-25 all First build, on the 2026 Q2 basis, from the intake brief at data/models/intake/tsm.json.
2026-08-25 verticals[teslaAi5], notes $473.80 Added a Tesla AI5 vertical with no history, starting 2027 Q1: one million half-reticle dies a quarter at about $150 of TSMC revenue each, growing toward 1.8 million as Optimus and clusters join. Moves base fair value from $472.80 to $473.80.