← Iris Energy Limited

IREN · Forward model · Bear case

The Bear case, 20 quarters out

Model as of

Each segment is projected from its own operating driver, rolled up into consolidated cash flow, and discounted back to a fair value per share. The assumptions below are editable — change them and every number on this page moves with them.

BASIS. Quarter ended 2026-06-30, labelled 2026 Q2 on this repo's calendar convention - IREN calls it Q4 FY2026 and its fiscal year ends 30 June. The label is checked against the actuals arrays, where the prior June quarter carries mining $180.330m plus AI Cloud $6.963m = $187.293m against the stored 2025 Q2 revenue point of $187.29m. Reported after the US close on 2026-08-27 from the 8-K Item 2.02 Exhibit 99.1, accession 0001878848-26-000051, with the FY2026 10-K indexed the same evening. The previous revision was built on the March quarter hours before this report landed and carried a READ THIS FIRST warning saying so; that warning is discharged. The June quarter is the first in which AI Cloud Services was the larger line - $70.5m against $66.7m of Bitcoin mining, 51% of revenue against 23% in March. SEGMENTS AND RECONCILIATION. Bitcoin mining and AI Cloud Services are IREN's only two reportable segments; both revenue and cost of revenue are disclosed per segment, there are no intersegment eliminations, and the two lines sum to consolidated revenue in all thirteen quarters carried here: $70.500m plus $66.700m equals $137.200m, matching the release's total revenue exactly. No split was invented and nothing was derived to fill a gap. Four historical points remain derived by subtraction from disclosed annual and nine-month figures and are flagged estimated (2023 Q2 and 2024 Q2 on both lines); the AI Cloud zeros for 2023 Q2 to 2023 Q4 are flagged estimated because the segment did not exist. The new quarter's two points are disclosed, not estimated. THE HASHRATE DISCLOSURE IS GONE. This is the most important finding in the roll-forward. Installed EH/s, average operating EH/s, Bitcoin mined, fleet efficiency in J/TH and electricity cost per MWh were all disclosed through 2026-03-31 and are all absent from the 27 August release; the FY2026 10-K carries annual durations only. The Bitcoin vertical is a capacity driver, so both of its state variables are now unobservable. Capacity is frozen at the last disclosed 38 EH/s at 2026-03-31, revenue per exahash-quarter is frozen at the March level of $3.0878m, and utilisation is a plug at 56.85% that reproduces the reported $66.7m - a derived 21.60 EH/s operating. The entire 40% sequential revenue decline is therefore booked to utilisation; the true split between fewer machines and worse Bitcoin economics cannot be recovered from public disclosure. That is tolerable only because this line is being switched off on a date. If the disclosure does not return and IREN were still running mining as a going concern, this vertical would have to be re-cut as a growth driver on segment revenue alone, with no hashrate anywhere in it. THE RUN-OFF IS DATED FOR THE FIRST TIME. The previous revision's note said no dated hashrate glide path had ever been published and the disclosure was 'over time'. On this call the CFO said: 'We currently expect mining operations to be effectively decommissioned by the end of December 2026.' The utilisation glide moves from 20% to 55% of the gap a quarter on that sentence, and it is the only driver level moved because the business changed rather than because the basis moved. A linear decommissioning from the 30 June level to zero on 31 December implies about $33.5m in the September quarter and $11.2m in December; 55% lands $30.0m and $13.5m, a two-quarter total within 2.7% of that. The glide leaves about $10m of tail across CY2027 against a stated zero, which is stated rather than tuned away. THE IMPAIRMENT IS STILL NOT A RUN RATE, AND IT IS BIGGER. $450.4m of impairment in this quarter and $638.8m for the year, 'primarily related to the decommissioning of Bitcoin mining hardware as sites are converted to support AI Cloud growth', plus a $102.1m decrease in the fair value of mining hardware held for sale. The previous revision carried a pre-announced estimate of roughly $520m; the actual charge came in at $450.4m in one quarter. All of it sits below the cash gross margin line and is in neither revenue nor margin, exactly as IREN's own adjusted EBITDA excludes it. Mining's margin is ($66.700m - $24.100m) / $66.700m = 63.87%, down from 68.21%; AI Cloud's is ($70.500m - $9.200m) / $70.500m = 86.95%, up from 86.33%. The release does not break segment cost of revenue into electricity, employee benefits and other direct expenses the way the 10-Q did, so that component detail is gone too. WHAT THE PRINT ARGUES AGAINST AND THIS REVISION DID NOT CHANGE. Three things. First, corporate overhead at 10% of revenue: implied cash corporate cost in the June quarter was $84.7m ($42.6m of mining gross profit plus $61.3m of AI gross profit less the reported $19.2m of adjusted EBITDA), or 61.7% of revenue, and the CFO guided September cash SG&A up another $40m-$50m sequentially. Ten percent is what the function should cost against a revenue base an order of magnitude larger; it understates the near-term dollar burn by more than the previous revision did, and it is left alone. Second, the AI Cloud capex intensity of 440%: it was fitted to $8.33m of ARR per gross MW, and this release restates the ladder in IT megawatts and quotes recent three-year contracts above $20m of revenue per MW (IT) - roughly $13m per gross MW at a 0.65 conversion, 56% more revenue against data centre and GPU capex the CFO says is up only 15-20%. That argues the intensity is now too high. It is left alone and flagged, because the print supersedes the old anchor without publishing a clean replacement per-megawatt capex figure. Third, the AI Cloud sequential growth rate of 150%: the trailing pace over the last three quarters is +135%, +94%, +110%, and the ARR bridge implies 170% for the September quarter. 150% sits between them and is left where it is. THE GUIDANCE THIS MODEL IS MEASURED AGAINST. IREN publishes no revenue or EPS guidance. The nearest thing is the CFO's ARR bridge: about $0.5bn of ARR exiting the June quarter, $1bn operating on 27 August after Microsoft accepted Horizon 1 on 13 August and carrying to the end of the September quarter, more than $4bn contracted by the end of the December quarter with the revenue effect landing 'predominantly in the March quarter'. Day-weighting $0.5bn over 44 days and $1.0bn over 48 across the 92-day September quarter gives average ARR of $761m and a revenue equivalent of $190.2m; the model's first projected quarter puts AI Cloud at $176.3m, a residual gap of -7.3%, and total revenue at $206.3m. On the full year, fiscal 2027 revenue is $2,465.1m and CY2027 is $6,028m, exiting at a $9.66bn annualised run rate against a 0.8GW (IT) ladder worth more than $16bn of ARR at the disclosed pricing - about 60% of it, the same deliberate under-shoot the previous revision carried. The two anchors are not consistent with each other and the model is matched to the near quarter, not tuned to both. CAPITAL. The $11,899,054,000 of twelve-month commitments that sized the corporate programme is superseded by explicit FY2027 capex guidance of approximately $25bn to $30bn, covering exactly the four quarters 2026 Q3 to 2027 Q2. The AI vertical's revenue-proportional capex spends $6.402bn across those quarters, so the programme carries $21.098bn and the four quarters total the $27.5bn midpoint. That is the single largest change in this revision and it more than doubles the near-term outflow. Against it the company puts $14bn of existing cash and committed GPU financing and prepayments, a targeted further $8bn of GPU financing and prepayments not yet raised, and an unencumbered data centre portfolio to borrow against. Free cash flow is negative in every quarter until 2030 Q4. NET CASH, SAME DEFINITION, RECHECKED. The previous value reproduces exactly: cash and restricted cash $2,213.274m less debt $3,687.832m less finance leases $274.256m = -$1,748.814m at 2026-03-31. Applying the identical definition at 2026-06-30 gives $7,619.5m of cash and restricted cash from the cash-flow statement, less $7,592.944m of debt ($169,370,000 current plus $7,423,574,000 non-current), less $243.796m of finance leases, equals -$217.240m. The cash figure is to one decimal in millions because the release prints it that way; the debt and lease figures are 10-K exact. Two things this definition deliberately does not do: it does not net the $1,842.6m of deferred revenue, which is customer money against undelivered service and is arguably the largest liability on the page, and it does not exclude the $1.7bn of restricted cash, most of which is set aside for Microsoft GPU capex. Both would make the number materially worse. Shares are 394,058,648 as of 2026-08-14, the most recent count disclosed, against 380,193,608 at 30 June; convertible underlying shares, the 30m NVIDIA investment rights at $70 and 14.8m of RSUs are charged nowhere in the fair value. SEASONALITY. Not recomputed, and still absent from both verticals. The previous revision's test - ratios to a centred four-quarter moving average - found a window-to-window spread that met or exceeded the entire seasonal signal on both lines. Adding one quarter does not change that, and the case is now stronger rather than weaker: the Bitcoin line is being decommissioned on a date and the AI line is a ramp off a base that doubled in a quarter. What moves these lines is the Bitcoin price, IREN's own decommissioning schedule and the date a data centre passes customer acceptance - none of them a calendar. WHAT THE MODEL PRINTS. Base case: 2026 Q3 revenue $206.3m (AI Cloud $176.3m, mining $30.0m); fiscal 2027 $2,465.1m; CY2027 $6,028m; terminal quarter 2031 Q2 at $10,474m with mining at zero; free cash flow negative in every quarter until 2030 Q4; fair value $51.01 against a $40.53 close. Bear -$31.58, bull $186.81, Roberts $169.92. The spread is enormous and that is the honest output of a company spending $27.5bn in a year to earn $2.5bn.

The bridge from capacity to revenue slips and the cost of waiting compounds. Mining revenue has fallen from $232.9m to $66.7m in three quarters and the company now says it will be effectively gone by the end of December 2026, while the AI line has to carry everything; $450.4m of impairment was booked in this quarter alone and $638.8m for the year; adjusted EBITDA fell from $59.5m to $19.2m on gross profit that barely moved, because cash SG&A ran at roughly $84.7m and is guided up another $40m-$50m sequentially; and FY2027 capex is guided at $25bn-$30bn against $7.6bn of cash of which $1.7bn is restricted. The company's own funding plan needs roughly $8bn of GPU financing and prepayments it does not yet have, plus data centre financing and corporate sources on top. Fair value goes negative, and that is the case rather than a rounding error: enterprise value falls below the gross debt, so the equity is the residual behind the lenders and the convertible holders.

IREN REVENUE MODEL

Latest: $5.70B (2031Q2E)

Period Value
2023Q2 $34M
2023Q3 $34M
2023Q4 $42M
2024Q1 $54M
2024Q2 $57M
2024Q3 $53M
2024Q4 $116M
2025Q1 $145M
2025Q2 $187M
2025Q3 $240M
2025Q4 $185M
2026Q1 $145M
2026Q2 $137M
2026Q3E $200M
2026Q4E $367M
2027Q1E $645M
2027Q2E $1.03B
2027Q3E $1.50B
2027Q4E $2.01B
2028Q1E $2.54B
2028Q2E $3.04B
2028Q3E $3.50B
2028Q4E $3.90B
2029Q1E $4.24B
2029Q2E $4.53B
2029Q3E $4.78B
2029Q4E $4.98B
2030Q1E $5.15B
2030Q2E $5.29B
2030Q3E $5.41B
2030Q4E $5.52B
2031Q1E $5.61B
2031Q2E $5.70B

What drives each segment

Bitcoin mining

Capacity × utilisation × price
Basis quarter$67M
Final quarter$4
Implied CAGR-96%
Share of revenue, final quarter0%
PV of segment cash flow$19M

A terminal cash line with a date on it now. IREN mines Bitcoin with ASICs at Childress and in British Columbia and sells it the same day, holding none. On the 2026-08-27 call the CFO said mining operations are expected to be effectively decommissioned by the end of December 2026 - the first dated run-off ever given, replacing the 10-Q's 'over time'. The company booked $450.4m of impairment in the June quarter and $638.8m for the year, primarily on decommissioning mining hardware as sites are converted, plus a $102.1m fair-value write-down on mining hardware held for sale. The model's job is to run the fleet to zero on that date while the cash it still throws off part-funds the GPU build - not to forecast Bitcoin.

Last four quarters
2025 Q3 $233M Reported
2025 Q4 $167M Reported
2026 Q1 $111M Reported
2026 Q2 $67M Reported
Block rewards and transaction fees, converted to USD or CAD and sold daily
Capacity energised 38 EH/s at the basis quarter 38 EH/s, unchanged, and now a fossil: it is the last installed-hashrate figure IREN ever disclosed, at 2026-03-31. The June release publishes no hashrate at all. Nothing is being added to it.
Capacity added 0 EH/s/qtr changing +0.0% per quarter Zero. No miner purchases: capital is going into GPUs, and the Childress halls are being emptied, not filled.
Utilisation 57% gliding toward 0% 56.85% is DERIVED, not disclosed. IREN stopped publishing hashrate with this release, so the energised share cannot be read off anything. It is $66.7m of June-quarter mining revenue divided by the $3.0878m per exahash-quarter this model holds flat, giving 21.60 EH/s operating, over the 38 EH/s installed. The whole 40% sequential revenue decline is booked to utilisation because the model holds the price flat by policy; the split between fewer machines and worse Bitcoin economics is unobservable and does not matter to a line glided to zero.
Revenue per EH/s $3.09M/qtr drifting +0.0% per quarter $3.0878m per exahash-quarter, held at the March 2026 level. IREN no longer discloses hashrate, so this can no longer be recomputed from the print; it is now an assumption carried forward, and the derived utilisation above absorbs whatever it gets wrong.
Bitcoin mining

Latest: $4.21 (2031Q2E)

Period Value
2023Q2 $34M
2023Q3 $34M
2023Q4 $42M
2024Q1 $53M
2024Q2 $54M
2024Q3 $50M
2024Q4 $113M
2025Q1 $141M
2025Q2 $180M
2025Q3 $233M
2025Q4 $167M
2026Q1 $111M
2026Q2 $67M
2026Q3E $29M
2026Q4E $13M
2027Q1E $6M
2027Q2E $2M
2027Q3E $1M
2027Q4E $461,387.29
2028Q1E $201,395.55
2028Q2E $87,909.16
2028Q3E $38,372.35
2028Q4E $16,749.53
2029Q1E $7,311.17
2029Q2E $3,191.33
2029Q3E $1,393.01
2029Q4E $608.05
2030Q1E $265.41
2030Q2E $115.85
2030Q3E $50.57
2030Q4E $22.07
2031Q1E $9.64
2031Q2E $4.21

Assumptions & reasoning

  • The margin is a cash gross margin: ($66.700m - $24.100m) / $66.700m = 63.87%, on the segment cost of revenue disclosed in the release. It was 68.21% in the March quarter. The release does not break that $24.1m into electricity, employee benefits and other direct expenses the way the 10-Q did, so the component detail carried in the previous revision is gone; only the segment total is disclosed now. The $450.4m of impairment booked in the June quarter, the $638.8m booked for the year and the $102.1m fair-value write-down on mining hardware held for sale all sit below this line and are excluded from both revenue and margin, exactly as IREN's own adjusted EBITDA excludes them. They are transition charges, not a run rate.
  • HASHRATE DISCLOSURE HAS BEEN WITHDRAWN. Installed EH/s, average operating EH/s, Bitcoin mined, fleet efficiency in J/TH and electricity cost per MWh are all absent from the 27 August release, and the FY2026 10-K carries annual durations only. Every one of those was disclosed through 2026-03-31. This vertical's driver is a capacity driver whose capacity and utilisation are now both unobservable: capacity is frozen at the last disclosed 38 EH/s and utilisation is a plug that reproduces reported revenue at a frozen price. That is defensible only because the line is being glided to zero on a dated schedule. If IREN were still growing this segment, the model would have to be re-cut on revenue growth alone.
  • The run-off is dated for the first time. The CFO said on the 2026-08-27 call: 'We currently expect mining operations to be effectively decommissioned by the end of December 2026.' The previous revision glided at 20% of the gap a quarter and retired 79% of the March run rate only by 2027 Q4, on the explicit note that no dated path had ever been published. One has now, so the glide moves to 55%. This is the one driver level moved because the business changed in a way the model already anticipated.
  • Sequential mining revenue: $232.9m, $167.4m, $111.2m, $66.7m over the last four quarters - -28%, -34%, -40%. The previous revision projected $88.9m for this quarter against $66.7m reported, so the old glide was 33% too slow. The new glide is faster than the trailing pace on purpose, because the trailing pace does not reach zero by December and the company says it will.
  • ERCOT demand-response and ancillary-services receipts are recorded in other operating income ($1.2m in the June 2026 quarter, down from $4.8m in March), not in Bitcoin mining revenue, so grid curtailment never touches this top line. It is netted against corporate overhead instead.
  • IREN sells its mined Bitcoin daily and holds none, so there is no treasury mark to model and no Bitcoin price exposure on the balance sheet - only inside the revenue per exahash, which this model holds flat.
  • Capex is zero on this line by assumption: Bitcoin expansion is over and every dollar of capital is going to GPUs and data centres. The retrofit spending that empties these halls is capital for the AI Cloud line, and is carried there.
  • The 2023 Q2 and 2024 Q2 points are derived by subtraction from disclosed annual and nine-month figures and are flagged estimated; the other eleven quarters are disclosed segment revenue. 2024 Q2 also crosses the IFRS-to-GAAP restatement boundary.

AI Cloud Services

Growth path
Basis quarter$70M
Final quarter$5.70B
Implied CAGR+141%
Share of revenue, final quarter100%
PV of segment cash flow-$12.81B

Contracted GPU capacity converting into recognised revenue on an acceptance schedule. IREN owns the land, the grid connection, the data centre and the GPUs, and sells GPU-hours on multi-year contracts. Revenue starts only on commissioning, testing and customer acceptance, which is why $4bn of contracted ARR sits beside a $70.5m quarter. In the June quarter this line passed Bitcoin mining for the first time - $70.5m against $66.7m, 51% of revenue against 23% in March. What is forecastable is how much of the 0.3GW (IT) targeted for 2026 and 0.8GW (IT) for 2027 is accepted, and when; the CFO's ARR bridge on the 2026-08-27 call dates the next three quarters of that for the first time. No quarterly energised-megawatt series and no utilisation figure exist, so this stays a growth line anchored on the ARR ladder rather than a capacity driver with an invented earning base.

Last four quarters
2025 Q3 $7M Reported
2025 Q4 $17M Reported
2026 Q1 $34M Reported
2026 Q2 $70M Reported
Bare-metal GPU cloud on multi-year contractsManaged AI cloud servicesStorage and ancillaries
Sequential growth +150.0%/qtr decaying toward +4.0% 150%, unchanged, and the decision not to move it is the point. IREN guides no revenue. The nearest thing in this print is the CFO's ARR bridge: 'We exited Q4 at roughly half a billion of ARR. It is $1 billion today following acceptance of Horizon 1 by Microsoft, and that will carry through to the end of the September quarter.' Day-weighting that across the 92-day September quarter - $0.5bn for the 44 days to Horizon 1's 13 August acceptance, $1.0bn for the remaining 48 - gives average ARR of $761m and a quarterly revenue equivalent of $190.2m, which would need 170%. The trailing sequential pace is the other bound: +135%, +94%, +110% over the last three quarters. 150% sits between them and lands the September quarter at $176.3m, a residual gap of -7.3% against the ARR bridge and above the trailing pace. The ARR bridge is an upper bound rather than a target because it assumes recognised revenue equals ARR divided by four on the day capacity is accepted, and the June quarter says it does not: $70.5m recognised against an exit ARR of about $500m.
AI Cloud Services

Latest: $5.70B (2031Q2E)

Period Value
2023Q2 $0.00
2023Q3 $0.00
2023Q4 $0.00
2024Q1 $567,000.00
2024Q2 $3M
2024Q3 $3M
2024Q4 $3M
2025Q1 $4M
2025Q2 $7M
2025Q3 $7M
2025Q4 $17M
2026Q1 $34M
2026Q2 $70M
2026Q3E $171M
2026Q4E $354M
2027Q1E $639M
2027Q2E $1.03B
2027Q3E $1.50B
2027Q4E $2.01B
2028Q1E $2.54B
2028Q2E $3.04B
2028Q3E $3.50B
2028Q4E $3.90B
2029Q1E $4.24B
2029Q2E $4.53B
2029Q3E $4.78B
2029Q4E $4.98B
2030Q1E $5.15B
2030Q2E $5.29B
2030Q3E $5.41B
2030Q4E $5.52B
2031Q1E $5.61B
2031Q2E $5.70B

Assumptions & reasoning

  • The starting margin is the disclosed cash gross margin: ($70.500m - $9.200m) / $70.500m = 86.95%, on the segment cost of revenue in the release. It was 86.33% in the March quarter, so scaling the fleet 2.1x did not yet load electricity onto it - most of the June fleet was still commissioning. The terminal 72% loads full electricity draw and site operating cost onto a fleet running near capacity; after the 10% corporate overhead charged separately that is about 62% at company level. Neither terminal is touched by this print.
  • THE CAPEX ANCHOR IS SUPERSEDED AND NOT RE-CUT. The 440% starting intensity was fitted to $19.3m of Dell hardware per GROSS MW, netted to $10.6m by a 45% prepayment, against $8.33m of targeted ARR per gross MW. This release restates the ladder in IT megawatts (0.3GW in 2026, 0.8GW in 2027, against the previous 480MW and 1,210MW gross - ratios of 0.63 and 0.66, so it is the same ladder in a different denominator) and says recent three-year contracts run at more than $20m of revenue per MW (IT) with a roughly two-year payback, against active discussions at about $25m. At a 0.65 IT-to-gross ratio, $20m per MW (IT) is about $13m per gross MW of revenue against the $8.33m of ARR the intensity was fitted to - 56% more revenue on capex the company says is up only 15-20%. That argues the 440% is now too high. It is left alone, because the print supersedes the anchor without giving a clean replacement per-megawatt capex figure, and because the FY27 capex guidance is carried in the corporate programme instead. A future revision has to settle it.
  • ARR is the company's own operating metric and is explicitly not revenue. It bills a full year at full utilisation on capacity that may have been live for a week, which is precisely the gap this vertical's ramp is trying to model. The bridge the CFO gave is the first time the gap has been dated: roughly $0.5bn exiting the June quarter, $1bn operating on 27 August after Horizon 1, more than $4bn contracted by the end of the December quarter, with the revenue effect of the December capacity landing 'predominantly in the March quarter'.
  • A monotone growth curve still cannot reproduce a step function, and the print makes the steps sharper, not softer. The curve lands the December 2026 quarter at $376m and the March 2027 quarter at $700m. Day-weighting the $1bn-to-$4bn ARR path across the December quarter gives something in the $325m-$450m range depending on how late 'late in the quarter' is, so December sits inside that range; the March quarter at a full $4bn ARR would be about $1,000m, so the model lands 30% below the ladder there. It exits CY2027 at a $9.66bn annualised run rate against a 0.8GW (IT) ladder worth more than $16bn of ARR at the disclosed $20m per MW (IT) - about 60% of it, the same deliberate stance as the previous revision. Below the ladder is the position, not a fit.
  • Mirantis and Nostrum both closed in the September 2026 quarter and report inside this segment, adding software, managed services and a European footprint. Neither contributes revenue to any actual carried here, neither has a disclosed contribution, and neither is modelled. The company says shorter-duration contracts and Mirantis managed services 'provide further revenue upside'; that upside is not in these numbers. Mirantis's roughly 12.6m shares are in the share count.
  • Horizon 1, the first of four 50MW (IT) liquid-cooled Childress deployments, was delivered to and accepted by Microsoft in August 2026, after this quarter closed, with NVIDIA Exemplar Cloud status on GB300 NVL72. Horizon 2 is commissioning, Horizons 3-4 are in late-stage construction targeting delivery in Q4 2026. Not one dollar of Horizon revenue is in any actual in this vertical.
  • The previous revision projected $84.1m for this quarter against $70.5m reported, so the AI line missed by 16%. The mining line missed by 33% the other way. Total revenue was projected at $173.0m against $137.2m - a 26% miss - and the shape of the miss says the same thing twice: the transition is running faster on the way down and slower on the way up than the curve had it.
Scenarios

Where each case comes from

Roberts case — primary sources

The primary sources this case is built from — filings, calls and posts. Where they are claims by an interested party rather than disclosures, every number in the Roberts column is what happens if they are taken at face value.

Valuation

From cash flow to fair value

Present value of free cash flow, 20 quarters-$36.56B
Terminal-year revenue$22.24B
Terminal-year EBITDA$13.15B
Exit multiple, on revenue2.2x
Terminal value$48.94B
Discounted at 15.0% a year, terminal value becomes$24.33B
Enterprise value-$12.23B
Net cash-$217M
Equity value-$12.45B
Shares0.39B
Fair value per share-$31.58
Against the deployed price of $44.68, as of -171%

15% matches the r40 CoreWeave model's rate for a levered, free-cash-flow-negative neocloud, and IREN's dilution and leverage stack got heavier in this quarter, not lighter: total debt went from $3,687.8m at 2026-03-31 to $7,592.9m at 2026-06-30 ($169.4m current plus $7,423.6m non-current) after $3.0bn of 1.00% notes and a $938m draw on the GPU financing facility, on top of $2,112.0m of ordinary shares issued in the same three months. Behind that sit a $3.6bn investment-grade GPU facility for the Microsoft contract at 6.0% and a new $2.8bn of non-investment-grade GPU financing including $2.4bn led by Blue Owl and PIMCO at 9.0%, plus - not counted as debt anywhere in this model - $1,842.6m of deferred revenue, which is customer money against service not yet delivered. Shares are 394,058,648 as of 2026-08-14 against 380,193,608 at 30 June; the 30m NVIDIA investment rights at $70 and 14.8m of RSUs disclosed at 2026-03-31 are charged nowhere in the fair value. The 3.0x exit on revenue prices the steady state beyond the build, not the terminal quarter: at 2031 Q2 this model still spends 58% of AI Cloud revenue on capex and free cash flow only turned positive two quarters earlier. The r40 CoreWeave model exits at 3.0x. IREN itself trades at about 22.6x fiscal 2026 revenue of $707.0m on a $15.97bn market capitalisation.

Read the other way round: at $44.68 the market is paying 4.9x terminal-year revenue, holding every other assumption on this page fixed. That is the number to argue about.

Capital programmes

Capex outside the verticals

Each vertical's capex is a share of its own revenue, which is the right shape for capacity that scales with sales. These are not that: fixed-size programmes with their own schedule that spend whether or not any segment grows. They are added on top, and they are why free cash flow dips in the years below.

FY2027 capex guidance ahead of revenue

2026 Q3 → 2027 Q2
Programme total$21.10B
Cash out$5.27B/qtr

On the 2026-08-27 call the CFO guided FY2027 capex of approximately $25bn to $30bn, covering exactly the four quarters 2026 Q3 to 2027 Q2 - IREN's fiscal year to 30 June 2027. That guidance replaces the $11,899,054,000 of twelve-month commitments the previous revision sized this programme on, and it is more than twice as large. The AI Cloud vertical's own revenue-proportional capex spends $6.402bn across those four quarters. This programme carries the $21.098bn difference so the four quarters total the guided midpoint of $27.5bn exactly. It belongs to no vertical: it funds Childress shells, Sweetwater 1, Mackenzie, GPUs and the Horizon retrofit together. The range is wide and the company says so; at the $25bn floor this programme would be $18.598bn and at the $30bn ceiling $23.598bn, worth roughly plus or minus $9 a share on the base case.

Quarter by quarter

The projected path

Quarter Bitcoin miningAI Cloud Services Revenue YoY EBITDA Capex FCF R40 PV of FCF
2026 Q3E $29M$171M $200M -17% $131M $5.91B -$5.78B -2905 -$5.58B
2026 Q4E $13M$354M $367M +99% $248M $6.39B -$6.14B -1576 -$5.73B
2027 Q1E $6M$639M $645M +345% $435M $6.99B -$6.56B -672 -$5.91B
2027 Q2E $2M$1.03B $1.03B $686M $7.64B -$6.96B -$6.05B
2027 Q3E $1M$1.50B $1.50B $985M $2.98B -$1.99B -$1.67B
2027 Q4E $461387$2.01B $2.01B +449% $1.31B $3.48B -$2.17B +341 -$1.76B
2028 Q1E $201396$2.54B $2.54B +293% $1.63B $3.84B -$2.21B +206 -$1.73B
2028 Q2E $87909$3.04B $3.04B +195% $1.93B $4.06B -$2.13B +125 -$1.61B
2028 Q3E $38372$3.50B $3.50B +134% $2.20B $4.16B -$1.97B +77 -$1.44B
2028 Q4E $16750$3.90B $3.90B +94% $2.43B $4.17B -$1.74B +49 -$1.23B
2029 Q1E $7311$4.24B $4.24B +67% $2.62B $4.12B -$1.50B +32 -$1.02B
2029 Q2E $3191$4.53B $4.53B +49% $2.78B $4.03B -$1.25B +22 -$821M
2029 Q3E $1393$4.78B $4.78B +37% $2.91B $3.92B -$1.01B +15 -$643M
2029 Q4E $608$4.98B $4.98B +28% $3.01B $3.80B -$795M +12 -$488M
2030 Q1E $265$5.15B $5.15B +21% $3.09B $3.70B -$602M +10 -$357M
2030 Q2E $116$5.29B $5.29B +17% $3.16B $3.60B -$434M +9 -$248M
2030 Q3E $51$5.41B $5.41B +13% $3.22B $3.51B -$288M +8 -$159M
2030 Q4E $22$5.52B $5.52B +11% $3.27B $3.43B -$165M +8 -$88M
2031 Q1E $10$5.61B $5.61B +9% $3.31B $3.37B -$60M +8 -$31M
2031 Q2E $4$5.70B $5.70B +8% $3.35B $3.32B $21M +8 $11M

Every row is projected. A year-over-year change is shown only where the quarter it compares against exists — an em dash means there is no comparable quarter, not a flat year.

Track record

Model revisions

Assumptions are marked to reality as each quarter prints. Every change is appended here, with the fair value the model produced at the time, so the model's own history stays visible.

DateFair value thenNote
2026-08-27 $24.59 First build, and knowingly on a stale basis. IREN reports fiscal 2026 Q4 and the full year to 2026-06-30 after the US close on this same date; the research brief is blocked on exactly that, and the model was built anyway. It must be rebuilt from the fiscal 2026 Q4 8-K Exhibit 99.1 once r40-earnings-data captures it, with basis 2026 Q2. Flagged unreliable until then.
2026-08-31 $51.01 Roll-forward from the 2026 Q1 basis to 2026 Q2, the quarter ended 2026-06-30 that IREN reported after the close on 2026-08-27 as Q4 FY2026 and full year. This is the rebuild the first revision said it was waiting for, and the READ THIS FIRST warning it carried is discharged; the unreliable flag is cleared with it, because its only stated cause was the stale basis. Actuals added to both verticals from the 8-K Exhibit 99.1: AI Cloud $70.500m and Bitcoin mining $66.700m, which sum to the reported $137.200m exactly. AI Cloud passed mining for the first time. Market inputs refreshed: shares 394,058,648 as of 2026-08-14, price $40.53 from the 27 August close, net cash -$217.240m on the same definition as before, verified by reproducing the old -$1,748.814m from the March balance sheet first. Two driver levels moved. The mining utilisation glide goes from 20% to 55% of the gap a quarter on the CFO's statement that mining will be effectively decommissioned by the end of December 2026 - the first dated run-off IREN has ever given, and the only reason to move a level in a roll-forward. Mining utilisation itself is now a derived plug at 56.85%, because THE HASHRATE DISCLOSURE HAS BEEN WITHDRAWN: installed and operating EH/s, Bitcoin mined, J/TH and power cost per MWh are all absent from this release and the 10-K tags annual durations only. Capacity is frozen at the last disclosed 38 EH/s and revenue per exahash at the March level; the split is unrecoverable and only tolerable because the line runs to zero. The corporate capital programme is re-sized from $8.845bn to $21.098bn so that the four quarters to 2027 Q2 total the CFO's FY2027 capex guidance midpoint of $27.5bn, replacing the superseded $11.899bn of twelve-month commitments; that single change is the largest in the file and the guidance range of $25bn-$30bn is worth about plus or minus $9 a share. Starting cash gross margins moved to the disclosed basis-quarter figures, 63.87% on mining and 86.95% on AI Cloud. Deliberately not changed: the AI Cloud sequential growth rate of 150%, which sits between a trailing pace of 110% and the 170% the CFO's ARR bridge implies for the September quarter, and which lands the first projected quarter 7.3% below that bridge; the 440% AI capex intensity, which the print argues is too high now that contracts run above $20m of revenue per MW (IT) against capex up only 15-20%, but which has no clean replacement anchor in the release; corporate overhead at 10% of revenue, against an implied $84.7m of cash corporate cost in the quarter, 61.7% of revenue, guided up a further $40m-$50m sequentially; and every terminal margin, terminal growth rate, exit multiple, discount rate and scenario delta. Tensions a future revision has to settle: whether the capex intensity and the corporate overhead can both stay where they are now that the FY2027 capex programme is $27.5bn; whether the ARR bridge or the trailing sequential pace is the right anchor for the AI line, which the March exit ARR would settle and which was never disclosed; whether the mining vertical should stay a capacity driver at all with no hashrate to put in it; and whether $1,842.6m of deferred revenue belongs in net cash. Scenario sources replaced throughout - the 10-Q impairment and commitments quotes, the 20 July ARR raise and the 480MW/1.2GW gross ladder are all superseded by this release and this call.